September
23, 2005
NOTICE
TO PLANHOLDERS
FOR CONSTRUCTION OF
TERMINAL
BUILDING ROOF REPAIR
COUNTY
PROJECT NO. W09571
ADDENDUM
NO. 1
I. Clarifications to various bid specifications
and requirements from questions received from
contractors:
- Special
Provisions, Section 4 – Beginning of Work, Time of
Completion and Liquidated Damages Paragraph A. Time
for Completion, should read as follows:
- All
contract work shall be completed within 15 working
days from mobilization to work site. Time will commence on the first day that the
Contractor mobilizes to the work site. A stop work notice will be issued for the 5-day
cure period and this time will not be included in the
completion time. All work must be completed no later than
October 31, 2005.
- Special
Provisions, Section 10 – Construction Details
Paragraph 10-1.07 Repairs - General, The following
paragraph should be added:
- Contractor
shall include in the lump sum price as work to be
included: Disconnecting
and removing the three (3) swamp coolers installed on
the roof. All
materials and debris associated with the removal of
the swamp coolers shall be the responsibility of the
Contractor. Contractor
shall remove the curb and make flush with the roof and
install 5/8" plywood over the opening and apply
roofing materials as required in this contract. Or Contactor may at its option, if a four-
sided curb mounting is in good shape, install a 20 ga.
galvanized sheet metal covering with 5/8" plywood
backing over the opening and incorporate the repair
and covering in such a manner as to prevent water
penetration.
Please
fill out "Addendum Acknowledgment" form of
the BIDDER'S BOOK on page BB4, verifying your receipt
of this Addendum.
DAVID
D. KNIGHT, DIRECTOR
DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
Susan
R. Klassen
Susan
R. Klassen, Deputy Director
Transportation /Operations
|