I. Clarifications to various bid specifications
and requirements from questions received from
contractors:
- Division
VII, Section 3 - Water Service Specifications Sheets -
Paragraph 3-2.1 should read as follows:
- The
Contract lump sum price paid for the Water Service
system shall include full compensation for furnishing
all labor, materials, tools, equipment and
incidentals, and for doing all the work involved in
the Water Service System as specified herein.
- Division
VII, Section 4 - Sewer Service Specifications
Sheets - Paragraph 4-2.1 should
read as follows:
- The
Contract lump sum price paid for the Sewer Service
system shall include full compensation for furnishing
all labor, materials, tools, equipment and
incidentals, and for doing all the work involved in
the Sewer Service System as specified herein.
- Division
VII, Section 5 – Gas Line Installation - Paragraph
5-2.1 should read as follows:
- The
Contract lump sum price paid for the Gas Line
Installation shall include full compensation for
furnishing all labor, materials, tools, equipment and
incidentals, and for doing all the work involved in
the Gas Line Installation as specified herein.
- Division
III, Section 4 – Standard Federal Equal
Employment Opportunity Requirements Part 4-1,
Paragraph F refers to the sponsor making a
directory of available DBEs. The latest
information regarding DBEs is available at the California
Department of Transportation web site and can
be downloaded at the following web
address:
http://www.dot.ca.gov//hq/bep/find_certified.htm
Then
selecting the Query option to obtain DBE information
by trade, location and other information.
- Division
III, Section 4 – Standard Federal Equal Employment
Opportunity Requirements Part 4-6, Paragraph A refers to a “Letter
of Intent” on page
4-6. This
form was omitted from the bid
documents in error and the referenced form
is attached to this addendum for use by
bidders.
- Division
IV, Section 1 – Miscellaneous Provisions for Airport
Construction – Part 1-1.4 Hangar Site
Coordination and Division of Contract Work is a
carry over from a previous bid document and does
not apply to this bid request.
- Division
VI – Entire Division - The phrase Airport Departure
Terminal was language used by the County
Architect’s office prior to the use of Airport Security
Screening Building used for the bid, therefore, all
requirements addressed as such apply to this
bid request.
- Division
VI, Section 1 – General Building Requirements,
the following clarifications should be noted:
- Part 1 – the overall building width is listed
as 36 feet. Due variations in building section widths this width maybe as
low as 35 feet and not more than 37 feet.
- Part 5, paragraph A – spacing between rails
can be greater than 4 (four) inches if the proposed
ramp height allows for greater spacing. Bidder is required to comply with Code requirements for
spacing.
- Plan
Drawing Set – Sheet 3 – First Floor Plan –
Dimensions, the following clarifications should be
noted:
- The carpet tiles are to be installed in the
hold room, vending area and security screening area. The linoleum is to be placed in the restrooms
and utility room. The vinyl composition tile is to be placed in
the hallway leading to the restrooms.
- The ramps to/from the building may be 4 (four)
feet wide instead of the 5 (five) feet as shown on the
plans, however, the top of the ramp shall be 5 (five)
feet by 5 (five) feet. If the bidder proposed to
install a 4 (four) foot wide ramp, the bidder shall
make a notation on the Substitution Request Form –
Proposed Substitution lines.
- The 2 (two) windows in the security area may be
combined into a single window with a width not less
than 6 (six) feet and aligned in such a manner to
avoid building section seams. If the bidder proposes to combine these
windows, the bidder shall make a notation on the
Substitution Request Form – Proposed Substitution
lines.
- Only DBE
requirements/good faith efforts
are required; the County considers DVBE, MBE, WBE etc.
as part of DBE.
- County
has approved the following manufacturer for the
equipment called for in Division VI, Section 10, Part
10522:
- JL
Industries – Academy Series Cabinet with the
“Saf-T-Lok” and the Cosmic: Multi-Purpose Chemical
Extinguishers. Supplier: DLR Sales Inc., (408) 988-1294
Please
fill out “Noted Addenda” of the BID FORM,
Section 00300, page 1, verifying your receipt of this
Addendum.
DAVID
D. KNIGHT, DIRECTOR
DEPARTMENT
OF TRANSPORTATION AND PUBLIC WORKS
______________________________________
Susan R. Klassen, Deputy Director
Transportation /Operations
Attachment (Available by contacting our office) |