February 13, 2002
NOTICE
TO PLANHOLDERS
FOR CONSTRUCTION OF
HANGAR
BUILDINGS
AND
RELATED
SITE IMPROVEMENTS
COUNTY PROJECT NO. W09536
ADDENDUM NO. 1
I. Changes to the
Special Provisions, Notice to
Contractors, Proposal and Contract
A. Section 00300, BID
FORM, page 1, Item 16 description: Change the
work "Gear" to the work "System."
II. Changes to Division III, Special
Site Conditions:
A. Page 4, Section 1-1.8, last paragraph, second
sentence: Change to read, "The County reserves the
right to deduct such costs from any monies due or which may
become due the Contractor or its surety."
B. Page 4, Section 1-1.10, second paragraph, first two
sentences: Change to read, "Construction stakes will be
set at constant offset from the building sides and ends.
Interior column lines will also be staked."
C. Page 5, Section 1-1.11, third sentence: After the
words "lump sum item," add "number 5."
III. Changes to Division IV, Technical
Specifications
A. Section 2, "Portland Cement Concrete,"
Section 2-3.1: Replace entire section with the following:
"2-3.1 The cost of hangar foundations and
slabs shall be included in Lump Sum Item 12,
"Concrete Foundations and Slab," and shall
include reinforcement steel, anchor bolts, other embedded
items, all material, labor, and all miscellaneous items
necessary to complete the work according to the Plans. The
cost of slab rock, sand and vapor barrier under the
concrete shall be included in Lump Sum Item 11, "Slab
Rock, Sand and Vapor Barrier." These prices shall be
full compensation for furnishing a complete and finished
floor slab and foundation for the building in accordance
with the Plans and Specifications."
B. Section 4, "Metal Building," Section
4-1.5.E.1: After the first sentence, add the sentence
"Also see General Condition 4.10."
C. Section 4, "Metal Building," Section
4-2.8.B: After the third sentence, delete the rest of the
paragraph beginning with the words " Rolling door
handles…"
D. Section 4, "Metal Building," Section 4-3.1:
Replace entire section with the following:
"4-3.1 The hangar building will be paid for
under separate Lump Sum Item 13 ("Pre-Engineered
Metal Building & Doors"), Item 14 ("One-Hour
Fire Wall - West Face"), Item 15 ("Utility Room
Framing"), and Item 16 ("Electric Bi-Fold Door
System"). The hangar fire sprinkler system will be
paid for as the separate Lump Sum Item 19, "Building
Fire Sprinkler System & Alarm Gear." The prices
shall include all labor, materials, tools, and incidentals
necessary to complete all above slab work according to the
Plans and Specifications. Building slabs/foundation work
will paid for as separate lump sum items under
Specifications Sections 1 and 2."
IV. Changes to Construction Drawings
A. Sheet 2, Hangar Layout Plan, Grading Note 3: change
first sentence to read:
"THE COUNTY SHALL ENLIST THE SERVICES OF A
REGISTERED GEOTECH- NICAL ENGINEER TO MONITOR THE
PLACEMENT AND COMPACTION OF MATERIALS."
B. Sheet 2, Hangar Layout Plan, Environmental Mitigation
Note 8: Delete note. Erosion control, hydroseeding and
landscaping are not required for this work.
C. Sheet 3, Utility Plan, SCWA Note 10: Delete note. The
construction drawings have already been submitted to the
Sonoma County Drainage and Sanitation Division by the
engineer during the permit process and will be reviewed by
Sonoma County Water Agency (SCWA).
D. Sheet 3, Utility Plan, Utility Room Detail B / 3: Add
dimension locating eastern face of east wall of utility room
at 9'-9" from outside face of concrete of west side of
hangar. Also add dimension of southern face of south wall of
utility room at 8'-2" from outside face of concrete of
north side of hangar.
E. Sheet 3, Utility Plan, Utility Room Detail B / 3: Add
note:
"UTILITY ROOM WALL FRAMING SHALL BE METAL STUDS
DESIGNED FOR MINIMUM 250 POUNDS PER FOOT BEARING WALL
CAPACITY. PROVIDE CEILING FRAMING AT 9'-0" ABOVE
FINISH FLOOR. CEILING JOISTS SHALL BE 2x6 DF-L GRADE NO. 2
AT 16" ON CENTERS SPANNING THE ROOM FROM EAST TO
WEST. JOISTS AND BLOCKING SHALL BE FASTENED TO THE WALL
TOP PLATE WITH APPROVED ANCHORAGE METHOD. PROVIDE
1/2" PLYWOOD SHEATHING ON TOP OF JOISTS. INTERIOR
WALL AND CEILING FINISH SHALL BE 1/2" GYPSUM DRYWALL
WITH TAPED JOINTS."
V. CLARIFICATIONS
A. Gypsum wallboard for fire-rated wall assembly need
only have joints taped with fire-rated tape. Painting is not
required.
B. The hangar building is not insulated.
C. Interior wall partitions shall be covered one side
with 28-gauge unpainted galvanized steel panels (see Spec.
Div. IV, 4-2.2.A). This includes the wall framing for the
utility room (steel panels on outside of wall). Interior
wall panel framing shall be galvanized steel members
designed for non-bearing use (except the utility room)
adequate for the required wall height at a
manufacturer-specified spacing.
D. Specification Section 4 – Metal Building, paragraph
4-2.8.E.5, last sentence: The sensor may be a flow sensor
which activates alarms when a sprinkler head is activated.
E. Drawing 11, Hangar Power, Telecom and Lighting Plan:
No wiring, fixtures or receptacles are required for the
future bathrooms shown wired to panel "xE-2,4."
Please fill out the "Noted Addenda" of the BID
FORM, Section 00300, page 1, verifying your receipt of
this Addendum.
EDWARD J. WALKER, DIRECTOR
DEPARTMENT OF TRANSPORTATION
AND PUBLIC WORKS
David
Knight
David Knight
Deputy Director |