| April 18, 2001
NOTICE
TO PLANHOLDERS
FOR CONSTRUCTION OF
CENTRAL LANDFILL SITE
EAST CANYON EXPANSION
PHASES I/II, PART 2
COUNTY PROJECT NO. W06888
ADDENDUM NO. 2
I. CHANGES TO THE SPECIFICATIONS
A. Changes to Division I, Bidding and
Contract Documents
1. Changes to the Notice Inviting Bids, Section
00020
Substitute revised Engineer's Estimate (Pages 3
and 4 of 5 attached)
2. Changes to Bid Form, Section 00300
Substitute revised Bid Form (Pages 2 and 3 of 5
attached)
3. Changes to Instruction to Bidders, Section
00100
Section 16, "Bid Protest," is
modified in part to read, "... before 5
o'clock p.m. (As determined by the clock on the
wall in the receptionist area of the Department of
Transportation and Public Works) of the fifth (5th)
business day following ...
Add Section 17, "Response to Certain
Inquiries From Prospective Bidders," as
follows:
a. Question: Where will the strippings be
stockpiled as required under Division IV, Section
02110, Subsection 3.4(C)?
Response: Strippings shall be hauled to the NW
Stockpile, Area 2 (6-inch minus).
b. Question: To determine the extent of
unsuitable material in the abandoned sedimentation
pond can pot holing be performed?
Response: Potholing is acceptable, but the
actual limits of overexcavation will depend on
field observations made by CQA Engineer. Potholing
may not be sufficiently deep depending on the
equipment used.
c. Question: Regarding Bid Item
17C, Geotextile Filter (7 oz/sy): Is the 7 oz/sq filter
fabric between the LCRS and Operations Layer the
same material as the 7 oz/sy separation fabric at
subgrade?
Response: Yes
d. Question: Regarding Bid Item
17D, Geotextile Separator (12 oz/sy): Is the bid
quantity correct for covering all of the tipping
apron and shaded area of the AB covered east
perimeter bench road?
Response: Refer to the revised
Engineer's Estimate (Section 00020) and revised
Bid Form (Section 00300) for Item 17D. The revised
quantity of 80,000 sf includes quantity for entire
plan area of the tipping apron and short approach
ramp, and the shaded area of the AB covered east
perimeter road, directly underneath the crushed
drain rock. Please note that in Detail 3 on
Drawing 8, the geotextile appears to extend only
12 feet from the grade separation. The geotextile
is to extend over the entire tipping apron, while
the geogrid only extends 12 feet.
e. Question: I understand that
there is slope repair work at the top of the cut
at the "hair-pin turn near monitoring well
DW-5. What is this work and how is it paid for?
Response: Some local instability has occurred
in the area of a cut slope in the eastern portion
of the site, close to monitoring Well DW-5 (shown
on Drawing 3). For the purpose of bidding, the
affected area is located between elevations
contours 316 ft and 300 ft above mean sea level in
Drawing 3. The repair of this area shall be
comprised of the following:
1. Remove sloughed-off materal
(estimated volume 200 cubic yards)
2. Remove failed material from the crest and
flatten the top of the slope back in the affected
crest area to a slope of approximately 3H:1V.
For the estimation purposes, this regrading shall
affect a plan area of 2,500 sq. ft.
3. Cut a v-ditch, 1-ft deep, with 1:1
side-slopes along the crest of the slope at a distance
of 4 feet from the regraed slope crest to intercept
flow from up-slope areas - total length of the
v-deitch is 150 lf.
4. Connect two 12-inc. CMP, one at each end of
the v-ditch, with Caltrans standard flared end
sections, to convey water from the ditch onto the side
of the road along each side of the slope.
Estimated total length of pipe: 225 ft.
5. This work is paid as lump sum under bid Item
No. 37.
f. Question: Regarding Items 8A and 8B, Drilling
and Blasting: Is there an estimated quantity of drill
and shoot for just the NW stockpile area?
Response: The approximate volume of the rock knobs
in the NW stockpile area is 7,200 cu yds.
g. Question: Is there a traffic count of
approximate number of public vehicles using the
planned haul route to the NW Stockpile area that can
be used to prepare Traffic Management Plan?
Answer: There will be changes in the traffic
patterns at the Central Landfill beginning as early as
May 2002. They can be described generally as follows:
- Beginning in May 2002 select loads of
refuse (materials which present the least risk of
damage to the lined floor of the Part 1 area ) will
be delivered to the Part 1 area. These vehicles are
likely to include 100 cu yd transfer vehicles and
side-loader refuse collection trucks. These vehicles
will share the existing Class 2 roadway between
Traffic Conflict Nos. 1 and 5 with heavy equipment
returning from the NW Stockpile. The remainder of
vehicles will continue to haul refuse to the
existing tipping apron of the 1971 permitting area
sharing the Class 2 roadway between Traffic
Conflicts Nos. 1 and 2.
- Beginning sometime during the summer of
2002, vehicles as large as articulating dump trucks
will be hauling refuse from the
yet-to-be-operational tipping building north of the
East Canyon, to the East Canyon Part 1 area. These
vehicles will share the existing Class 2 roadway
between Traffic Conflict Nos. 1 and 5 with heavy
equipment returning from the NW Stockpile.
- Until the above mentioned transfer
station becomes operational, the full volume of
traffic bringing refuse to the Central Landfill will
share the existing outbound haul route between
Traffic Conflict No. 1 and 2 with heavy equipment
hauling to the NW Stockpile.
- After the above mentioned transfer
station becomes fully operational, a fraction of
vehicles will continue to utilize the existing Class
2 roadway between Traffic Conflict Nos. 1 and 2.
These vehicles include commercial yard waste
collection vehicles, self-haul yard and wood waste
customers, and compost sales customers.
- As the rock extraction project southeast
of the NW Stockpile (and directly south of the
compost sales area) is no longer in operation,
Traffic Conflict No. 3 is no longer a
significant conflict with rock trucks back hauling
to the local quarry.
- Traffic counts as tallied at the Central
Landfill cashier booths for the months of June and
July 2001 are presented below.
Average Daily Traffic Count at
Central Landfill |
| |
Private
Vehicle |
Garbage
Compactors |
Debris
Boxes |
100 yd3 Transfer
Trucks |
Yard Waste Commercial Haulers |
June 2001 |
431 |
58 |
44 |
33 |
36 |
July 2002 |
439 |
59 |
46 |
34 |
35 |
h. Question: Regarding Division III, Section
1.13, Maintaining Traffic, page 8 of 24, paragraphs
6 and 7 seem to be in conflict. Can the public
traffic be placed in a reversing, one-way
configuration between 7 a.m. and 4 p.m., controlled
by flaggers?
Response: Paragraphs 6 and 7 have been replaced
by the language shown below under Changes to
Division III, Special Provisions, Section 1.13,
Maintaining Traffic.
i. Question: Regarding Bid Item No. 25; 24-Inch
Diameter CMP Downchutes: Does Caltrans Standard
Specification Section 69: Overside Drains apply to
this work? If it does, will you provide more
information and detail on the anchor assemblies,
pipe joints and mitered joints that would be
required?
Response: Consistent with Division III Section
1.17, the downchute CMP should conform to provisions
of Section 66 of Caltrans Standard Specifications
for the CMP pipe. Section 69 of Caltrans also
applies to this work. In either case, the standard
joints anchor assemblies as per applicable Caltrans
Specifications shall apply.
j. Question: Regarding Bid Item No. 30B; Drainage
Ditch - 3-in. Thick Fiber-Reinforced
Shotcrete-Lined: What are the pay limits? If the pay
limits are to the "CDS" unit, where is it
located? If the ditch extends south of the Part 2
limits of excavation, has the ditch been constructed
to the shape shown on Section 1 on Drawing 8?
Response: The pay limits extend from Control
Point 519 to the drop inlet at the head of the
downchute leading to Sedimentation Pond No. 6
(Coordinate N15209.82, E16490.38. Between Control
Points 519 and the CDS unit (labeled as
"Existing CDS Unit" on Drawings 3 and 4) a
new ditch must be excavated where none currently
exists and shall be shotcreted. Between the CDS Unit
and the drop inlet mentioned above, an existing
ditch must overexcavated to conform to the
dimensions shown on Section 1 of Sheet 8, and
shotcreted. Reinforcing the ditch as the drop inlet
is an existing sack concrete berm (approximately 3
feet tall and 8 feet long). This berm is to be
shotcreted 3 inches thick, both sides. The ditch at
the roadway intersections at the top and bottom of
the 22% grade, shall be "softened" at the
direction of the Engineer so that vehicles can drive
across the ditch.
k. Question: Regarding Item 30A; Drainage Ditch -
2-ft Deep Erosion Mat Lined: What material
specification applies to the erosion mat fo the
ditch lining?
Response: The erosion mat used in the mat lined
ditches shall be one that is intended for use as
ditch lining material by the manufacturer and shall
be capable of retaining its function over a period
of at least 3 years from date of installation. The
material to be used shall be P300 manufactured by
North American Green, or its equivalent. Adequacy of
the material shall be determined by a submittal to
the Design Engineer. The erosion mat shall be
installed in a manner consistent with manufacturers
recommendations.
l. Question: What requirements are there on the
NW Stockpile as to maximum slope?
Response: Stockpiles in the NW Stockpile area
shall have slopes no steeper than 2.5H:1V, with 15
foot wide benches at 50 ft intervals (measured
vertically, starting at the toe of the slopes.
m. Question: The following are missing from the
bound specification book
- Division I, Section 00411,
Bidder's Bond
- Division IV, Section 02772, Sacrificial
Geomembrane, page 8 of 10
- Division IV, Section 02281, Fiber Rolls
(entire section)
Response: The missing items are
attached to this Addendum No. 2.
n. Question: Will existing recycling center be
relocated prior to award of contract and how is the
removal of the grade separation within recycling
center paid for?
Response: The recycle center will be moving north
across paved entrance road to a new facility. Bidders
should note that earthwork may have to commnce
elsewhere and a claim for delays will only be granted
when earthwork cannot proceed without the recycle
center being relocated. Removal of grade separation,
including piles, will be paid for under lump sum for
clearing, grubbing and stripping, and modification to
Division IV, Section 0210, 4.1A is made by this
reference.
o. Question: Since the quarry operation at the
Central Landfill has been completed, is there an
actual traffic conflict at the Traffic Conflict No. 3
as shown on drawing No. 2?
Response: As it is correct that rock trucks are no
longer hauling from the Central Landfill, Traffic
Conflict No. 3 is of minimal conflict.
B. Changes to Division III, Special Provisions:
1. Section 1.13, Maintaining Traffic, page 8 of 24,
paragraph 6 (which begin with, "A minimum of one
traffic lane ...") and paragraph 7 (which begin
with, "Lane closures or traffic stoppages
...") are replaced with the following language,
"Public traffic heading between Traffic Conflict
Nos. 1 and 2, can be placed in a single reversing,
one-way configuration controlled by flaggers, which
would allow scrapers to operate in their own dedicated
lane, so long as all scrapers run in a tight formation
(pack) thereby allowing both lanes to serve the public
when scrapers are not driving on the public roadway
between Traffic Conflict Nos. 1 and 2. Scrapers shall
use the outside lane (adjacent down hill slope).
Individual lane closures shall be restricted to the
time it takes to run the pack of scrapers between said
Traffic Conflicts. Should scrapers not maintain pack
formation to the satisfaction of the Engineer,
resulting in excessive delays to the public, Engineer
may revoke lane closure option. Should hauling to NW
Stockpile be performed using trucks, which by nature
will be evenly spread over the haul loop, lane closure
will not be allowed."
C. Changes to Division IV, Technical Specifications:
1. Section 02227, Subsection 4.2 (A),
Payment, a third sentence is added to read, "Such
price shall include construction of new ditches and
reworking (overexcavating) of existing ditches as
described in Addendum No. 2."
2. Section 02281, Fiber Rolls, is attached to this
Addendum No. 2
3. Section 02225, Operations Layer, Subsection
2.1(C) second sentence is modified in part to read,
"... exhibits a hydraulic conductivity of 1 x 10 -4 cm/sec or less, Gravel-Filled Finger Drains
shall be constructed. The specification for finger
drains is included below."
The third sentence under Subsection 2.1(C) is
deleted.
The following paragraphs are added to Subsection
2.1(C):
"The design for a modified operations layer
shall be as follows: Gravel filled drains shall be
installed within the operations layer in the cell
floor area to enhance the flow of leachate into the
granular LCRS layer that underlies the operations
layer. One drain should be placed along the
center-line of the floor area, immediately above the
LCRS pipe. Two additional drains should be placed,
one each along the toe of east (which will wrap
around on the north side) and west slopes. Feeder
drains should be placed in a chevron pattern joining
the drains along the toe to the central drain. The
locations of the feeder drains will be provided by
the Design Engineer prior to construction. The total
estimated length of drains required is approximately
2,500 lf.
The drains shall be located in 3-ft wide trenches
going into the full depth (2 ft) of the operations
layer, lined with a 7 oz/yd2 non-woven
geotextile such that the bottom of the drains will
be in contact with the geotextile separator that
lies on top of the granular leachate collection and
removal system (LCRS) layer. (This 7 oz/sy non-woven
geotextile is the same material as Bid Item 17C.
Note that the geotextile material quantity for
finger drains is not included in Bid Item 17C, but
shall be included in the cost per lineal foot of
Gravel-Filled Finger Drains provided in Bid Item 36.
Clean, uniform gravel (having particle size of
between 1-in. and 1.5-in. with a maximum of 5% by
weight passing the #200 sieve) shall be placed
within the geotextile to a full thickness of 2 ft
(i.e. level with the operations layer) and the
geotextile shall be wrapped over the top, with a
minimum of 2 ft overlap.
Note that equipment will not be
allowed directly on top of the geotextile (which
lies over the granular LCRS layer). Equipment may be
allowed over soil placed on top of the geotextile.
Schedule of equipment loads allowed over soil on top
of the geotextile is provided in Section 3.6B of
Construction Specification 02714 (Geotextile).
A schematic cross section through the Gravel-Filled
Finger Drains within the Operations Layer is shown
below:"
Please fill out the
"Noted Addendum" (Division I, Section 00300,
page 1) verifying your receipt of this Addendum.
EDWARD J. WALKER, DIRECTOR
DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
___Alex
Sebastian_______________
Alex Sebastian
Civil Engineer
(Attachments are on file
with the Department of Transportation and Public Works) |