March
26, 2002
SONOMA
COUNTY
DEPARTMENT OF TRANSPORTATION
AND PUBLIC WORKS
NOTICE
TO PLANHOLDERS
FOR CONSTRUCTION OF
CENTRAL LANDFILL SITE
EAST CANYON EXPANSION
PHASES I/II, PART 2
COUNTY PROJECT NO. W06888
ADDENDUM NO. 1
I. Changes to the Notice Inviting Bids (Section
00020):
A. PRE-BID WALK-THROUGH is
modified in part to read, "The mandatory pre-bid walk-through is rescheduled for 10:00 a.m.,
Tuesday, April 9, 2002. The
pre-bid walk-through originally scheduled for Thursday
March 14, 2002, was cancelled as plans and
specifications were not available prior to that
date. The conference will commence within the
Refuse Operations Headquarters Building, Central
Landfill, 500 Mecham Road, Petaluma, CA 94952. BIDDERS
NOT ATTENDING THIS MANDATORY MEETING WILL NOT BE
ELIGIBLE TO BID ON THE PROJECT. ORANGE SAFETY
VESTS WILL BE REQUIRED IN THE FIELD TO OBSERVE SITE
CONDITIONS. Representatives from theCounty
and Geosyntec Consultants will be present to discuss
the project, receive questions, and conduct a tour of
the project. At all other times, bidders' access
to the Central Landfill....."
B. GENERAL INFORMATION, Section B is modified in
part to read, "Sealed bids will be received by
the Clerk of the Board of Supervisors, Room 100A, 575
Administration Drive, Santa Rosa, California, 95403,
until 3:00 p.m. on
Tuesday, April 23, 2002, at
which time they will be transferred to the County
Administrator's Office Conference Room where they will be publicly opened........."
Please fill out "Noted
Addendum" (Division I, Section 00300, page 1)
verifying your receipt of this Addendum.
EDWARD J. WALKER, DIRECTOR
DEPARTMENT OF TRANSPORTATION
AND PUBLIC WORKS
Alex
Sebastian
Alex Sebastian
Civil Engineer |