NOTICE TO PLANHOLDERS
FOR CONSTRUCTION OF
CENTRAL
DISPOSAL SITE
EAST CANYON EXPANSION
PHASE IV
COUNTY PROJECT NO. W06887
ADDENDUM NO. 4
The
following changes are hereby deemed to be a part of the
Contract Documents in full effect as if originally
included.
1 Refer to Division I, Section 00020-NOTICE INVITING
BIDS:
Delete
entire Section and add the attached Section.
2. Refer to Division I, Section 00100, INSTRUCTIONS TO
BIDDERS, subsection 11.1:
Delete
reference to "Document 00600" and replace with
"Document 00660."
3. Refer to Division I, Section 00300-NOTICE TO
CONTRACTORS:
Delete entire
Section 00300 and add the attached Section 00300.
4. Refer to Section 00421, "QUESTIONNAIRE AND
FINANCIAL STATEMENT FORM":
Clarification: Division I, Item 9 of Addendum No. 3 referred to a
"new" Section 450. Actually Section 450 was included in the original
Specifications and should not be considered new.
5. Refer to Division I, Section 430-LIST OF
SUBCONTRACTORS:
Delete
entire Section 430 and add attached Section 430.
6. Refer to Division IV, Section 02718, subsection 3.5
(F):
Second
sentence: After
the word "occur" add the word
"between"
Change
“Friday” to "Thursday."
7. Refer to Drawing No. 5 related to the gas main
installation:
Change Station
50+00 to Station 41+00
Change Station 50+32.30 to Station 41+32.30
Please fill out "Noted Addendum" (Division I,
Section 00300, page 1) verifying your receipt of this
Addendum.
DAVID D.
KNIGHT, DIRECTOR
DEPARTMENT OF TRANSPORTATION
AND PUBLIC WORKS
Randall S.
Forbes
Randall S. Forbes, Design Manager
Civil Engineer