Project Name:  AB 2928 Phase 3 Overlay Projects Various County Roads Spring 2002

Project # C01321, C01322, C01323, C01303

 March 7, 2002

SONOMA COUNTY
DEPARTMENT OF TRANSPORTATION
AND PUBLIC WORKS

NOTICE TO PLANHOLDERS


FOR CONSTRUCTION OF

AB2928, PHASE 3
OVERLAY PROJECTS
VARIOUS COUNTY ROADS
SPRING 2002

COUNTY PROJECT NOS. C01321, C01322, C01323, C01303

ADDENDUM NO. 1

 I.    Changes to the Special Provisions, Engineer's Estimate and Bidder’s Book: 

A.  The location of the River Road overlay has been changed to P.M. 17.49 to P.M. 18.19.

B.   Please replace the Engineer's Estimate for River Road (C01321) pages SP-3, BB-3, BB-16, and BB-17 with attached "Revised" SP-3, BB-3, BB-16, and BB-17

We anticipate issuing the Notice to Proceed on April 15, 2002.

Please fill out the Addendum Acknowledgment sheet in the Proposal (page BB-7 of the Bidder's Book) verifying your receipt of this Addendum.

EDWARD J. WALKER, DIRECTOR