Skip to Content | Accessibility Assistance
Printing Header
Project Name: Santa Rosa Avenue Storm Drain Phases 1 & 2

Project # C00017, C03009

September 16, 2003

NOTICE TO ALL PLANHOLDERS
FOR CONSTRUCTION OF

SANTA ROSA AVENUE
STORM DRAIN
 PHASES 1 & 2 
 
COUNTY PROJECT NOS. C00017, C03009
   

ADDENDUM NO. 2

I.    Changes to the Notice to Contractors in the Special Provisions Book: 

A.  Delete the last sentence in the first paragraph of the "Notice to Contractors," page SP-1, and substitute therefore the following: 

"Award of this project to the lowest responsible bidder is scheduled for September 30, 2003 by the Board of Supervisors.  Should bid irregularities arise such that the low bidder cannot be determined by the 30th then the award will be postponed until the bid irregularities are resolved and the award or rejection of bids can be rescheduled for the Board of Supervisors." 

Please fill out the Addendum Acknowledgment sheet in the Proposal (page BB-5 of the Bidder's Book) verifying your receipt of this Addendum.

DAVID D. KNIGHT, DIRECTOR
DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS

____Geoff Power_________________
Geoff Power, Civil Engineer