Bid Results
FOR CONSTRUCTION OF
COMMUNITY
DEVELOPMENT BLOCK GRANT PROJECT
WEST AVENUE IMPROVEMENTS
(COUNTY ROAD NO. 78061)
PHASE I
BETWEEN
HEARN AVENUE AND METAXA COURT
P.M. 10.00 TO P.M. 10.17
NET LENGTH 0.28 KILOMETER
COUNTY PROJECT NO. C00009
|
BID DATE & TIME
|
March
21, 2002 at 3:00 p.m.
|
|
CONTRACT
|
West
Avenue Improvements, Phase I
|
|
ENGINEERS
ESTIMATE
|
$143,244.00
|
| PROJECT
NO. |
C030009 |
|
RANK
|
BIDDER
|
AMOUNT
|
|
1 |
North
Bay Construction, Inc. |
$125,392.60 |
2 |
Tri-County,
Inc. |
$143,299.89 |
3 |
Ghilotti
Brothers, Inc. |
$144,810.50 |
4 |
Nelson
Construction |
$155,797.75 |
5 |
Ghilotti
Construction Co. |
$169,827.60 |
LOW
BIDDER'S SUBCONSTRACTORS |
|
A & D
Concrete |
|
| |
Able Fence |
|
| |
Golden State
Traffic Service |
|
| |
Mike Brown
Electric |
|
| |
Striping |
|
|