| Fiscal Year: |
13-14 |
Segement: |
2B |
Description: |
Class 1 through State Park including 1,100 linear feet of boardwalk with 6" toe railings and street crossings at Bay Shore and Bay Flat Roads |
Right of Way: |
State Parks |
Feet: |
1,680 |
Miles: |
0.32 |
Estimated Cost: |
$900,000 |
| Fiscal Year: |
13-14 |
| Segement: |
3D-1 |
| Description: |
Class 1 along Eastshore Road right of way and boardwalk along tidelands to Tides Wharf parking lot. Includes approximately 2,350 feet of 8' wide boardwalk with 54" high railings. |
| Right of Way: |
Public Tidelands, County Road |
| Feet: |
3,300 |
| Miles: |
0.63 |
| Estimated Cost: |
$1,531,000 |
| Total Feet: |
4,980 |
||||||||
| Total Miles: |
0.94 |
||||||||
| Total Estimated Cost: |
$2,431,000 |
||||||||
| Estimated Funds: |
|
||||||||
| Total Funds Needed: |
$ 2,242,000 |

| TLC: |
Transportation for Livable Communities - Federal Funds |
| PMF: |
Park Mitigation Fees - Local County Funds |
| MM: |
Measure M Sales Tax - Local County Transportation Funds |
| CSP: |
California State Parks (In kind Services not billable to project) |
| SCC: |
State Coastal Conservancy - State Funds (Con) |
| CIAP: |
Coastal Impact Assessment Program |
| R/W: |
Right of Way |
Return to Bodega Bay Pedestrian & Bike Trail Project