Funding Summary - Bodega Bay Pedestrian and Bike Trail

An estimated 6.3 million dollars is needed to complete construction of the Regional Parks Department phases of the Bodega Bay Pedestrian and Bicycle Trail (BBT) Project including the Cheney Creek Bridge Trail (completed in 2008), proposed Coastal Prairie Trail Segments 1B & 1C, Harbor Coastal Trail-Segments 3D-2, 5B & 6B and North Harbor Coastal Trail-Segments 2B & 3D-1. The following is a summary of funding received and currently available to Regional Parks for these segments of the project.

$6.3 million Total Funding Needed

Funding Received

  • $   350,750   State Coastal Conservancy (SCC)
  • $   100,000   Measure M Sales Tax
  • $     80,000   Park Mitigation Fees (FY 06/07 - 07/08)
  • $   530,750   Total Funding Received

Funds Available

  • $   270,000   Measure M Sales Tax 2009 Programmed Funding
  • $   535,000   Transportation for Livable Communities (TLC)
  • $     75,000   State Coastal Conservancy (SCC)
  • $   390,000   Park Mitigation Fees (FY 09/10 - 12/13)
  • $   114,000   Coastal Impact Assessment Program (CIAP)
  • $1,384,000   Total Funds Available