Funding Summary - Bodega Bay Pedestrian and Bike Trail
An estimated 6.3 million dollars is needed to complete construction of the Regional Parks Department phases of the Bodega Bay Pedestrian and Bicycle Trail (BBT) Project including the Cheney Creek Bridge Trail (completed in 2008), proposed Coastal Prairie Trail Segments 1B & 1C, Harbor Coastal Trail-Segments 3D-2, 5B & 6B and North Harbor Coastal Trail-Segments 2B & 3D-1. The following is a summary of funding received and currently available to Regional Parks for these segments of the project.
$6.3 million Total Funding Needed
Funding Received
- $ 350,750 State Coastal Conservancy (SCC)
- $ 100,000 Measure M Sales Tax
- $ 80,000 Park Mitigation Fees (FY 06/07 - 07/08)
- $ 530,750 Total Funding Received
Funds Available
- $ 270,000 Measure M Sales Tax 2009 Programmed Funding
- $ 535,000 Transportation for Livable Communities (TLC)
- $ 75,000 State Coastal Conservancy (SCC)
- $ 390,000 Park Mitigation Fees (FY 09/10 - 12/13)
- $ 114,000 Coastal Impact Assessment Program (CIAP)
- $1,384,000 Total Funds Available
Return to Bodega Bay Pedestrian & Bike Trail Project